August 29, 2017
Updates To CO 9/US 6 Paving Schedule
The schedule for final paving operations is as follows:
Wed, Aug 30 — Crews begin at 7 a.m. on the southbound right lane of CO 9, from Ruby Ranch Road to 3rd Street with completion in the afternoon. All businesses will remain open, although access may be limited at times. Motorists are encouraged to use Adams Avenue to navigate around the temporary closures.
Fri-Mon, Sept. 1-4 — No paving
Tue-Thu, Sept 5-7 — 7 pm to 7 am. Night paving of the I-70 interchange, ranging from 3rd Street on CO 9 to West Anemone Trail on US 6. All highways including the on- and off-ramps will remain open, although detours may be in place. Please follow posted signage and pay close attention to flaggers’ directions when traveling through the project. Questions? Call 970-409-4099.